Hi, I was wondering if anyone has come across the following scenario.
I live in a seismic area, where the design and construction of buildings have to comply to Eurocode 8, which requires a minimum of a 4cm(1.6 inches)( seismic joint)between all old and new structures and between structures on...
Is it possible to do a computer model on the effects of soldier piles with ground anchors on neighbouring ground as well as the effect of this on adjacent structures. So it is a combination of Geo - technical and structural modelling, showing stresses on the ground, under foundations, lateral...
My neighbour has illegally installed 17x 3 strand lateral tie cables in my property, total length of each cable is 14m. The lateral cables are permanent and hold up a retaining wall 10m high x 20m long. An underground garage structure has been built against the retaining wall, but the tension on...