Dear's,
we came across in the specification, the ship owner requirements to "Design pressure of deck piping 40barg and lower design temperature -55°C. All cargo isolation valves shall be top entry cavity free torque seated eccentric c‐type ball valves.
cryogenic applications LNG cargo handling...
Hi,
can anyone advice me pipe internal flushing, how it can be done using "Balloon", possible to send me procedure / pictures of how it looks like to plan for cleaning on-board of vessel, and this can perform cleaning to the "Vertical Omega" piping. please advice!
REgards,
RK
Hi,
we have an issue on site with the SS316L pipe internal joints areas "Oxidation / Corrosion" marks, need and expertise advice how this can be handled to clear the marks any other solution w/o proceeding with circulation cleaning, reason being asked for all the pipes are installed on-board of...