I know this topic has been discussed a lot here, but I have a situation with a twist that I haven't seen discussed elsewhere.
For the overwhelming majority of the run I'm concerned with, it's a textbook three-conduit system directly out of the examples in NFPA 70. For about ten feet before it...
Looking to get consensus here. I have an application where we can either open a 13.2kV vac breaker (feeding a 2000kVA transformer) or a 3000A 480V unit substation breaker (fed by said transformer). There are about 1200A worth of load on the 480V side. Both breakers can be opened remotely...
We have a situation where we are planning to parallel conductors of different length and characteristics.
We have a 15kV M-T-M switchgear with paralleled transformers (automatic tap changer controls fully commissioned for paralleling), but the gear is run with the tie normally open. This gear...
I'm hoping to get some advice for integrating some parallel generators and a step-up transformer at an industrial plant.
We have (4) 1MW generators which will be paralleled and backfeed a single 480-13.2 step-up transformer. This will feed a service rated MV ATS and pick up the entire plant...