We are issuing a deductive change order. And the contractor is not including the overhead and profit in the cost proposal.
Our argument is they should because in the contract, it reads the following:
"For Work to be deleted by Change Order, the reduction of the Contract Sum shall be computed...
On the baseline schedule, the contractor put down 9 days drill and pull 1100 ft of pipe underground (horizontal directional pull). During the operation, they encountered rocks which slowed down their operation. The rocks were not on the geotechnical report so it is fair for the contractor to...
A contractor on my project was using horizontal drilling to pull a fusible pvc 20 ft deep in the ground. As they were pulling, drilling fluid came through the existing joints along an old trench. And supposedly, the ground heaved 1". My question is it possible for the ground to heave when the...
I have a project where the contractor is using Horizontal Driving to install fusible PVC in the ground. During the reaming operation, they were running into rock which damaged their drill bits. Now they are claiming cost for repair to their drill bits and delay in their operations. There was...