We are adding a spillback line for the chemical injection pump that is on a lower deck (25ft) below the chemical storage tanks. Does it matter whether the spillback is routed to the suction of the pump or to the tank?
In years past, the facility had to shut-in to perform inspections on the dry oil tank. However, we are trying to find ways to bypass the DOT so we do not stop production. What criteria must be considered when evaluating if the DOT can be bypassed (ie. RVP, dew point, etc.) There is a bulk oil...
Currently, two centrifugal pumps in parallel run in lead and lag to move water from the tank to the water system. The discharge of the pump feeds a bladder tank that's supposed to keep the pressure constant and minimize the pump from turning on/off constantly. However, the bladder is busted...