My project plan consists of a Master.mpp and a dozen or so separate .mpp files for various parts of the project (Development, Validation, Documentation, Overhead, etc...). All of these files are in a single directory called "Project Plan". Recently, I made a copy of that directory for...
Hello again
In addition to accounting for the actual time and resources needed to hold a large extended meeting (see previous thread entitled "Meeting Overhead"), I'd like to add a task for "meeting preparation" ahead of the meeting (prep ends when the meeting starts), and "meeting follow-up"...
Hello. I'd like to account for the overhead of formal design review meetings in terms of resource usage and cost accounting. Say my meeting will be two four-hour sessions, over two days.
What I've done to try and account for this is to enter the task as a fixed duration of two days...
I was given a project in which the calendar is set to use 6.4 hours per day, 32 hours per week and 16 days per month. I believe these settings were used in an attempt to account for overhead -- time that the resources don't get to spend on the actual project.
First, if I create a task of 5...