I've taken the new 16 hr SE Exam (Buildings) and passed. The test is heavily weighted toward seismic design category D. I do not have any design experience in SDC "D," so this made it difficult for me, but I was able to overcome this with a lot of studying focusing on SDC "D." If you can pass...
This may be a little late for your decision, but I can give you my experience. I recently passed the new 16 hour SE exam (building exam for essay portion.) I highly recommend taking some type of review course for this extremely hard test. I took the School of PE review course for the vertical...
My understanding of the MSJC 2011 Appendix B and the NCMA TEK 14-23 is that any and all masonry walls that fill in the open space of a concrete or steel framed building is considered "infill." The definitions of "infill" and "bounding frame" in the MSJC 2011 are pretty straight forward. This...
I wander if the architect is applying the 2 hour fire SEPARATION rules to a 2 hour fire rated wall. The 2 hour fire separation intends for the structure to be separated from the fire wall, but I do not believe this should be applied to a fire rated stair well.