Hi There,
We have a 1500kVA Emergency Generator (star wound) onsite that is connected to the Essential Services Board (800kVA), with a synchronizer to allow to load test. The Essential Services Board is connected to the 11kV Site Switchboard via 2 x 11/0.415kV 1500kVA Dyn11 Transformers (6%...