A 20 ft thick layer of fill (SP material) has been placed in a ravine to level out a site
for construction. The contractor claims that the fill has been compacted to 95% of the modified
Proctor value but can produce no test results except for the top 5 ft. A borehole is drilled and
SPT tests are...