Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. m1ke99

    Crane Runway Beam - Lateral Deflection

    I'm evaluating an existing building for an increased crane capacity. Client wants to go from 30 Ton to 35 Ton. Overhead double girder, top running. Everything is looking okay, except for lateral deflection on one of the crane runway beams. The runway beam on one side is on the exterior...
  2. m1ke99

    Concrete Slab - Integrity Reinforcement Cut

    On a two-way concrete slab (w/ drops at columns) contractor forgot to add some piping sleeves near a column and has decided it would be okay to core without scanning for rebar. I looked in the hole and they cut 1 of the 3 bottom integrity bars. Anyone have recommended repair details?
  3. m1ke99

    building addition - 5 story wood

    I am looking at an expansion for an existing 5 story wood frame structure. (Residential) The existing doesn't have capacity for additional gravity loads so the structure will need to be independent. With the effects of settlement (footings) and shrinkage, I am concerned about the differential...
  4. m1ke99

    Existing post-tensioned slab

    I need to review and existing slab for a 3 storey building and discuss coring options with the owner. How can I tell without drawings if the 2nd floor slab is post-tensioned?
  5. m1ke99

    April 2016 structural PE

    That was a tough exam. Definitely missed a couple of questions...
  6. m1ke99

    Slab on Grade - Control Joint Location

    If I have a 20ft x 20ft room with a sump in the middle, is it best to run the control joints diagonally from the corners of the room to the corners of the sump pit? Or saw cut down the centre with orthogonal pattern?
  7. m1ke99

    Slab on Grade Loading

    Do I need to consider slab on grade loads (Dead and Live) on adjacent grade beams or foundation walls? Is there a difference if I key and dowel the slab into the grade beam? I have heard mixed advice. The most common approach I have heard is to take 1 meter of tributary width of the slab on grade.
  8. m1ke99

    Moment Frame

    Yes the design is a portal frame, the question is more about the fixity of the connection. Stiffeners are required? Any other design guides for this type of connection?
  9. m1ke99

    Moment Frame

    The foundation is an existing slab on grade that I don't want to rely on for moment capacity. The lateral loads are relatively light (interior equipment stand).
  10. m1ke99

    Moment Frame

    Is it possible to create a rigid frame to resist lateral forces using a connection as shown in the attached sketch? Continuous beam running on top of columns. http://files.engineering.com/getfile.aspx?folder=a6ff9427-9c46-4ded-bddc-c9440ef4ceaf&file=Moment_Frame.pdf
  11. m1ke99

    Continuous Beam

    I have a two consecutive simple span steel beams, designed accordingly for uniformly distributed load and only positive moment (wl^2/8). If the beam at the central column makes the beam continuous over the column, I will have a negative moment at the column. 2 questions: 1) If I do not have...
  12. m1ke99

    Perimeter beam design

    I am reviewing the structural steel design for a school. The building is 2 storeys with steel beam/column framing and open web steel joists. The walls consist of vertical steel studs between columns. The studs are connected at the bottom to the concrete floor slab and connected to the top at the...

Part and Inventory Search