Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. swsweld

    Double Weld or Single Weld on Atmospheric Tank Built to ASME Sect XIII-NDE Requirements

    Heavenside1925, We are the end user. Fabrication is complete, the vessel is stamped and I do think it was an internal decision to build it to ASME Sect VIII instead of API standards. I came in late to this project and I don't have a good answer on why Sect VIII. Originally, we were under the...
  2. swsweld

    Double Weld or Single Weld on Atmospheric Tank Built to ASME Sect XIII-NDE Requirements

    We have a disagreement on the NDE requirements for an Atmospheric Tank built to ASME Sect. XIII, SB-575 UNS N10276, P-43 material-Hastelloy. All parties agree that the exterior welds require PT on all welds. The disagreement is on the interior welds (longitudinal, circumferential and nozzle...
  3. swsweld

    P22 Quenched Pipe Weld

    The weld was 'sprayed-for lack of a better term' during weld out. PWHT has not been performed. This weld had greater than 25% deposition so I'm not worried about root cracking but it was not controlled cooling as required in 'Interruption of Welding" It was a rapid cool down, therefore I think...
  4. swsweld

    P22 Quenched Pipe Weld

    metengr, Thanks for the feedback. Your advice seems reasonable. We don't have hardness test requirements on P22 that must be met, but comparing the results of the 'quenched weld' to a couple of welds on the same line that were not 'quenched' should provide valuable information. In some cases...
  5. swsweld

    P22 Quenched Pipe Weld

    Hello All, Code is ASME B31.1 2014. Issue is a 32" P22 Sch60 pipe weld just below flush that had water inadvertently released and 'quenched' the weld enough to cause the heat treat chart to drop below the WPS inter-pass temp. The temp. dropped from 500F to 250F briefly. 400F-600F is WPS...
  6. swsweld

    P91 Pipe Temporary Weld Question

    metengr and weldstan, I appreciate the replies. It's one of those questions that can't be found specifically in the codes (at least I don't think it can) but relies on experience, best practices and common sense...of which you both have plenty. Thanks again.
  7. swsweld

    P91 Pipe Temporary Weld Question

    Hello All, We are missing a component that welds in-line on a VPR (vertical pipe rack) module being constructed in the fabrication shop. The component will not available until after the pipe rack is up-ended at site. It is now horizontal and will be shipped that way. ASME B31.1 We want to weld...
  8. swsweld

    Hydro Test and Pipeline Design

    The test pressure isn't always 1.5 of design pressure or MAOP. Different codes have different test criteria. Some Classes in B31.8 are only 1.1, 1.25 or 1.4 of design pressure. B31.3 states in 345.4.2 PT=1.5 PRr where P p internal design gage pressure PT p minimum test gage pressure Rr p ratio...

Part and Inventory Search