I agree that mid-point would be a good location for concrete psi(strength) test and possibly be ok for slump too. I feel the slump test should be an initial test performed from the first portion( 1/4 cu yd) poured. If slump test failed at mid-point, then you have 4 1/2 cu yds of concrete out of...