For shift the power for Load sharing is no problem.
But possibility to synchronize breaker point A that condition is both GTG & STG already synchrone with integration system 33kV.
It's possible? specifically in phase angle fedeer to feeder breaker point A. thanks
Hi sandeeoelect1
Shift load from GTG to STG2 because a maintenance schedule for bus 11kV and GTG. Bus 11kV at GTG must be power off but keep the load still power on.
Regards,
Hi scottyUK
thank you for reply
In this case i want to transfer the power flow from GTG to STG 2 without power off at the load. Is possible if i configure this system with synchronize at breaker point A? or any procedure to transfer the load with switch off the syncronize of GTG/STG2 or 33/11...
Dear experts
I want to configure new alternative power for electrical power system. You can look the system in image attachment.
this picture:
The condition is GTG and STG2 synchronize with system integration 33kV.
I want to ask about the synchronize fedeer to feeder in breaker point A. Is...