ScottyUK / Crshears,
We are still in the design phase and no construction contract has been awarded. I apologize if I implied we were that far along.
Our plan of action would have the contractor do as much pre-outage work as possible. When you ask, "Have you installed new motor control...
Crshears,
You are correct in situation I attempted to describe. Based on what you are saying it would appear I am underestimating the time requirement for the main MCC feeder cut-over.
Just to be clear the minimum time allotment you indicate above is ONLY for the final few feet of feeder...
Davidbeach,
"Vital" loads are currently undefined. We have the Single Line Drawings available but the Owners are responsible for providing which of those loads cannot be in a sustained outage. In general the loads we anticipate being considered "vital" would include ventilation equipment...
Good Day. I am working on a project in a facility where the owners have several loads they have deemed "vital" to operations and cannot be in an outage for a prolonged period of time.
Our specific task in this project is the replacement of the upstream distribution equipment including...