Thank you guys so much for that answers.
jraef: You are correct about facilities not paying attention to what's on and what's off are usually not on their list of priorities. Thank you very much for the helpful information.
waross: Thanks for the reply. I appreciate the information regarding...
So if the MCC already exists, then I would still just add up all the FLAs and subtract it from the bus rating? From what I read, most MCC connected loads are actually larger than the demand loads. So if I turned everything on, then the total FLAs would actually be higher than the bus bar...
Hey Everyone:
First time posting so I hope this goes well.
I work at a company that has some old MCCs that are still in use. I am trying to collect all the loading information for said MCCs. I am just wondering if anyone has any examples of how to do a load list.
What I want to know is what...