Not sure, the film did not show an area more dense or rejectable by code. I would also agree that rt SHOULD BE PERFORMED , but I am wondering from a code/legal standpoint. By code, is it or is it not required to rt this joint a second time
Hi, I have an odd situation that I cannot find an appropriate answer to.
A closure weld has been performed, and subsequently RT was also performed. The rt passed and was acceptable but today this joint became internally accessible. The root could now be visually inspected (there was no plan for...