Clarifiers are 160' in diameter so client/engineer will not approve a single pour. They base slabs were poured in 8 pies (per contract drawing construction joints) and they initially wanted the topping joints to mimic the slab joints. We would love to pour in a single shot but they argue the...
thread592-122542
Referencing above thread from 2005. Looking for any input regarding the placement of a 2" topping being finish with clarifier equipment/screed. We are looking to pour in 3 concentric circles, pouring the inner and outer circles on the same day and the middle circle on a second...