  1. Jness

    2 inspections per vessel

    Hi All, My company manufactures 2ft x 4ft all the way up to 3ft x 8ft ASME CODE pressure vessels. We manufacture about 15 a week and currently have to have the AI inspect the vessel before we weld the second head on and then again after it is welded/at pressure test. Is there a way to design...
  2. Jness

    Hydro-static Tests Need a faster way

    Hi All, My company manufactures 2ft x 4ft all the way up to 3ft x 8ft ASME CODE pressure vessels. We manufacture about 15 a week and currently are spending hours just filling and pressure testing these. Theres got to be a faster way to do this. Does anyone have a good set up that they could...