I have a tender to construct 50 km CS oil UG pipeline, 8", the soil is sand
the construction period starting from ROW till hydrotesting is 12 months
I am preparing the level 1 of the plan along with manpower and equipment plan
Can you please help me in this matter
I prepared the construction...