Guys as per your suggestions, i have consulted my process dep. and they have provided following process design conditions;
Maximum Shut-off Pressure 1479 kPa
Extreme Transient Temperature 65 0C
Maximum Operating Temperature 45 0C
Minimum Operating Temperature 25 0C
Under above mentioned...
Hi members!
I am working on a pipeline project in Libya. We are to design, analyze and procure HDPE pipe for approximately 25 KM in length. I am concerned about HDPE pipe design code / standard. Is there any code, standard for calculation of pipe wall thickness? Your guidance in this regard will...
Hi Folks !
I am working on a project and a little bit confused about galvanizing coupling. I have to tap a stainless steel chemical injection line in Carbon Steel Blind Flange. Question is do i have to isolate CS from SS with some means. Any governing ASME Code or standard for reference will be...