  1. David RP

    Sewer Lift Station Detailing

    I'm also a fan of what HTURKAK proposed. Bear in mind that the kicker joint should be high enough so as not to allow the waterstop to contact the reinforcing steel below it. A good rule of thumb is that the distance from the waterstop to the rebar is 1.5 times the size of the largest aggregate...
  2. David RP

    WWTP - Concrete Structures with Joints

    The waterstop does not need to be installed at the center of the joint. It is perfectly acceptable to install the waterstop off-center. What you want to bear in mind, is the waterstop should have one half waterstop width in concrete cover. Example: A typical 6-inch waterstop would require 3...