Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. R. Pradhan

    Hydro test chart recorder graph

    if we consider test pressure holding for 1 hour, is there different ( Pressure and temperature) chart record graph / PAPER for 100 bar , 200 bars, 400 bar and 1000 bars available for analog tester ???? change will be only gra
  2. R. Pradhan

    valve test

    Hi Experts We want to do valve shell test, can we do hydro test with pipeline system ? please guide ! best regards Pradhan
  3. R. Pradhan

    300 % NDT for pipeline CODE DNVGL ??

    Dear Thanks everyone for your support Regards Pradhan
  4. R. Pradhan

    300 % NDT for pipeline CODE DNVGL ??

    thanks everyone for reply BASE ON DNVGL -F101- 2017 Still Client is forcing to do UT+RT+MT where as it DNVGL - D.1.4.4 it is optional and somewhere it is saying we have to go for UT +RT so bit confuse please guide APPENDIX D NON-DESTRUCTIVE TESTING (NDT) ( Page – 392/393) Methods of NDT...
  5. R. Pradhan

    300 % NDT for pipeline CODE DNVGL ??

    Hi All we are doing pipeline project and base is DNVGL client is asking for 300 % NDT for all girth weld when using manual UT is it required 300 % ?? Also is it compulsory RT + UT (Manual ) ?? me or my team do not have experience on this please guide best regards Pradhan

Part and Inventory Search