All, thank you for the valuable inputs. We are the site installer. We want to make sure all the valves are OK prior to installation into the pipelines.
Danlap, I am referring to shell hydrotest and not the seat test.
I read through ASME B16.34, API 598 & EN12266 and couldn't find any...
Hi,
Is there any restriction in hydrotesting of multiple valves connected in series to meet ASME B16.34. We have 200+ of globe valves to go for hydrotesting, to reduce the test lead time we are thinking of connecting 5 valves in series and test them at the same time using test pressure and...