I understand that rule of payment like a lumpsum payment with the data shown on the design drawings. In any case, base on the actual site condition the pile toe can be shallower or deeper than in the drawings but the payment will be unchange. Am I right?
Hi Everyone,
I have a question related to the measurement method in my project as follows:
In our preamble of the Bill of Quantities statement measurement method for piling work as:
“Measurement of piling shall be by the length of piles installed from the underside of the structure reinforced...