Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. TripleAYUDA

    Number of hours to design excavation project

    Diaphram wall or sheet pile wall etc...
  2. TripleAYUDA

    Number of hours to design excavation project

    Dear all I would like to know from your experience the number of hours you put in to design an excavation project (less than 20m) assuming you have all geotechnical data, lab tests, and loads ready. thanks
  3. TripleAYUDA

    4000 kN lateral load on piles

    I am designing a pile foundation to support 8000 kN axial load + 4000 kN lateral load + 600 kN eccentricity moment. Piles are 1m in diameter and 23 meters deep Soil profile mostly clay: first 10 meters Su = 80kpa and the rest Su = 200 kpa and groundwater level at the surface; From analysis...
  4. TripleAYUDA

    Three column in one pile cap

    Dear all I am designing a pile foundation for a new building. the columns are closely spaced so I decided to place them on a single pile cap with a depth of about 1 meter, each column will transfer the load to the individual pile. The pile cap will also be connected with ground beams. Is...
  5. TripleAYUDA

    Owner geotechnical engineer problems

    Axial loads that go up to 2500 kN 25mm settlement required SPT is not accurate in clay, still, clay parameters such as Su were obtained from SPT and PI. The building is in the same area, but the building owner already complained about visual cracks which the owner want to avoid.
  6. TripleAYUDA

    Owner geotechnical engineer problems

    Yes, the procedure is unusual. Well, the design firm mentioned that they knew well the area reason why they were confident that the soil is dense sand. The owner did not have an engineer on the owner's side at the time project was being discussed, this was done later after project drawings...
  7. TripleAYUDA

    Owner geotechnical engineer problems

    Hi (1) The contract required the foundation to be defined after soil investigation. (2) The designer ignores it and proceeds with a shallow foundation and drawings were produced. (3) Geotech was hired and requested Geotech investigation turn out piles are required. (4) Designer requested...
  8. TripleAYUDA

    Owner geotechnical engineer problems

    Hi guys Thanks for the feedback, the client's position is that in case the designer fails to comply with the contract condition, we will hire another Geotech firm to finish the design since we have retained part of the total amount of the design fee which will be used for payment. He act...
  9. TripleAYUDA

    Owner geotechnical engineer problems

    Le99 No one agreed with the shallow foundations solution. It was the designer alone decision. If this was found during construction, the client would probably suffer more aggravated costs with delays etc...
  10. TripleAYUDA

    Owner geotechnical engineer problems

    A detailed shallow foundation drawing was prepared by the structural engineer. There was no analysis of shallow foundation e.g. settlement etc... Shallow foundation not yet constructed since we decided to stop until piles are designed In terms of cost, the client has no problem paying for...
  11. TripleAYUDA

    Owner geotechnical engineer problems

    Hi dik The was no EOR when the decision was made. I only came to take this job after decisions were already in place by the designer mostly. A nearby building foundation was also designed on a shallow foundation but also without any soil report. The building owner complained about wall cracks...
  12. TripleAYUDA

    Owner geotechnical engineer problems

    The client was responsible for executing the geo investigation BUT the designer/structural engineer was confident that they knew the site ground condition and advised the employer to discard the investigation until I start working for the client and immediately order the investigation. The...
  13. TripleAYUDA

    Owner geotechnical engineer problems

    To clarify I am the owner/client representative for this project. Our contract required that a soil investigation be carried out prior to designing the foundation but it was completed ignored by the designer and a shallow foundation was designed using presumptive bearing capacities which turn...
  14. TripleAYUDA

    Owner geotechnical engineer problems

    Dear all I am the client's representative, working with a 2 story building that was initially designed to be supported on a shallow foundation, no geotechnical investigation was carried out and it was simply assumed that the ground is dense sand with an allowable bearing capacity of 100 kpa...

Part and Inventory Search