The minimum weld required for olet to run pipe as described below as per ASME 31.3, but if same followed for SS run pipe , there be distortion.
so is there any excuse for SS olet welding.
328.5.4 Welded Branch Connections
(i) Figure 328.5.4F shows additional integrally reinforced branch...
As per B31.3 Impact test acceptance criteria, what should be minimum absorbed energy for Duplex SS , it’s given there only lateral expansion values. What about energy min energy to be...
Is there any limit for maximum soaking time during PWHT as per construction code or Metallurgy.
Say example LTCS P number:1, A333., construction code B31.3 process piping.
There is minimum soaking time limit as per construction code , but what about any maximum any limit on maximum soaking...