  1. E. Kermendy

    CYMgrd or ETAP simulation of PV and SS earthing grid interconnected.

    Thanks for answering. I copied the response, to write on it, our way to see the Electromagnetic world, with Ohm's law lenses. A ground fault at the substation will cause a ground potential rise near the ground grid at the sub and near the location of the fault. = AGREE With no...
  2. E. Kermendy

    CYMgrd or ETAP simulation of PV and SS earthing grid interconnected.

    Is CYMgrd or ETAP able to model the interconnection of a solar PV farm earthing grid interconnected with its interconnect substation earthing grid? The issue is that when injecting the short-circuit currents from the substation into the earthing grid of the PV plant, it does not support it...
  3. E. Kermendy

    Transference of earth fault currents to PV Plant Earthing System from interconnect substation

    We are involved in a 90 MW PV in construction project. The interconnect station (33/132 kV) is exactly as those shown in IEEE 2778, neighboring the PV farm. The GPR is quite high (about 8 kV) at substation due to several reasons, as 22 kA short circuit power, quite small switch yard (40x45 m)...
  4. E. Kermendy

    Earthing design of 50 MW PV Plant and 30/220kV Substation ( separated 7 km)

    By coincidence, we have a similar problem with a 90 MW PV in construction project, but here the interconnect station (33/132kV) is exactly as those shown in IEEE 2778, neighboring the PV farm. The GPR is quite high (about 8 kV) at substation due to several reasons, a 22 kA short circuit power...