Dear all,
Contractor has been installing a new boiler assembly in our plant to add steam producing. We already inspected inside boiler and found the arrangement superheated tubes touch each other with no special support. We are worry tube vibration will appear during boiler operation and tubes...
I will install several new pumps as crude transfer pumps from storage tank to mixing tank. The pump will be operated in large various of capacity. The plant operating mode and availability of specified crude are reasons. Choosing pump specification to be difficult due to much different of...
Installing a Spill Back Flow
I will install several new pumps as crude transfer pumps from storage tank to mixing tank. The pump will be operated in large various of capacity. The plant operating mode and availability of specified crude are reasons. Choosing pump specification to be difficult...
Dear all guys,
We have been performing project Built a Water Tube Boiler Cap.110 ton/h, specification standard refer to ASME. In near future we will erect the Boiler Stack, nevertheless I have still to prepare the Erection Procedure for Boiler Stack. If any guys have a standard procedure for...
Dear all guys,
We have been performing project Built a Water Tube Boiler Cap.110 ton/h, specification standard refer to ASME. In near future we will erect the Boiler Stack, nevertheless I have still to prepare the Erection Procedure for Boiler Stack. If any guys have a standard procedure for...
Thank you and appreciate for your responds. I had read ASTM A106, and specifically on sec. 18 about Workmanship, Finish and Appearance. Nevertheless, in my opinion the problem is different. ASTM cites the imperfections caused by workmanship, but in my case, the problem caused by environment...
Dear All,
Thank you and appreciate for your responds. I had read ASTM A106, and specifically on sec. 18 about Workmanship, Finish and Appearance. Nevertheless, in my opinion the problem is different. ASTM cites the imperfections caused by workmanship, but in my case, the problem caused by...
Dear all friends,
We have a contract to Built a Boiler Cap. 110 t/h complete with its supporting equipment and pipe lines with a local contractor. We are now in phase constructions and some materials already in site. We had a problem when carbon steel pipes come in site, while we inspected them...
Dear all friends,
We have a contract to Built a Boiler Cap. 110 t/h complete with its supporting equipment and pipe lines with a local contractor. We are now in phase constructions and some materials already in site. We had a problem when pipes come in site, while we inspected them by visual...