I need everyone's opinion on the effectiveness and long term duration of Chemical Injection to stabilize Eagle Ford Shale type soil with PVR of 7-10 inches and PI 52-60. Construction area is near the Dallas area. It is for residential purposes. Has anyone heard of ECSS 3000 (IS 2500)? How...
My geotech engineer designed a foundation plan calling for the select fill and the piers, he is not too fond of the water injection method. He did however suggest that if the chemical injection is done properly, and the soil is retested to verify that desired results were achieved, that this was...
I need information on the best foundation design for this type of soil. I do have a geotech engineer report. I have been given the following options and will like to know which is more effective and economical: removal and refill with select fill up to 60" and 15 foot piers, water or...