ok, so i have the ball rolling a little on this one now, however - looking at the initial efficiency rating it is only considering the hours that the staff are available and i class this as availability and not efficiency. Thought when considering efficiency, it would have to combine performance...
ok, am a little wiser now but where has the 2080 come from?
it also provides me with an efficiency rating of 1.05, what does this represent, should it be less than one?
On the availability issue to find the availabilty of staff i have worked out the amount of time the staff are actually...
been working on a formula to try and calculate staff efficiency working with the following headings,
Availability=Total budgeted man-hours-No.of man-hours unavailable/Total budgeted hours = 98%
Performance=Completed w/orders * Target Time Taken / Work orders pending * Time taken =...
looking in to remote condition monitoring of radar sites,problem being have a large slewring ring 6ft in diameter rotating at 7rpm. Some of the sites are situated around the coasts and north scotland.Just worried that the use of accelerometers and shock pulse methods will not distinguish between...