  1. kjy313

    Hydrotest min. holding time

    I just remember that 30 minute is min. holding time in ASME Sec.VIII, Div.1. But I could not remember where this statment is. Could anyone let me know the location of this statement? Many thanks in advance.
  2. kjy313

    Protective treatment for bare carbon steel

    These vessels are separators for oil and gas plant. Mr. eyec, could you explain "shrink wrap" in detail? It sounds a cousin of food wrap. If hydrotest will be undertaken with alkine water, is it possible for the carbon steel internals to be passivated?
  3. kjy313

    Protective treatment for bare carbon steel

    Three vessels will be shipped oversea after hydrotest. There are the uncoated carbon steel internals in these three vessels. I worry that the internals can be corroded during sea transportation and storage. I expect that the vessels will be serviced after 6 months later. Could any one recommend...
  4. kjy313

    Hydrotest for the vessel involed in the train incident

    The problem is that the vessels wil be installed in oversea no USA or Canada. No jurisdiction is in that country. And the accident is not exposed to heat. Anyway, this matter is almost finalized. I proposed the conditinal hydrotest as followings to the client. They seem to be satisfied with my...
  5. kjy313

    Hydrotest for the vessel involed in the train incident

    I would like to correct the details of the incident agaist the above tread as below. "the three disconnected flatbed cars having our three vessels traveling at 3 to 4 mph collided with other set of cars traveling at 4 to 6 mph in opposite direction. The vessels tie-down broke loose and vessels...
  6. kjy313

    Hydrotest for the vessel involed in the train incident

    The incident details are followings. "the three disconnected flatbed cars having our three vessels traveling at 3 to 4 mph collided with other set of flatbed cars with my vessels traveling at 4 to 6 mph in opposite direction. The vessels tie-down broke loose and vessels slid forward approx 2 ft...
  7. kjy313

    Hydrotest for the vessel involed in the train incident

    Thanks for reply Mr. Metengr. You are right. They asked us to pay the expense of the hydrotest. These vessels were made from carbon steel(SA516-60). And I found the following statment in ASME Sec.VIII, Div.1. UCS-56(f)(6):"The vessel shall be hydrostatically tested after making the welded...
  8. kjy313

    Hydrotest for the vessel involed in the train incident

    I have three vessels which are involved in the train incident during transportation. These vessels are U Stamped vessels. During the survey, I couldn't find any visual damage, dent and scratch on pressure vessels. So, I and a vendor decided to do MPI for detecting the possible crack. And we...