I am using MS Project to plan schedule for a 3 shift operation. I wish to schedule two 10 min and one 30 min break in each of the shifts.
Can I show these breaks on the Gantt chart in form of non-working time?
If yes, then can I make the task/s to automatically split at these breaks?
Thanks...
I have created a project plan in MS Project. I have a gantt chart assosiated with it. The Gantt bars have the names of the indicvidual task that they represent.
The names of the individual tasks are long in some cases.
I would thus like to format the text (i.e. names) inside the bar. i.e...