Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. brizstruct

    AS3600-2018 Commentary

    Rapt Congratulations to getting the commentary out. The discussion is valuable and the references and thoughts in the commentary provide extra information and guidance. The committee gets a beating every so often. Thank you for not giving up on your effort with the committee and the rest of us...
  2. brizstruct

    Displacement Induced Seismic Force

    I would suggest that it might be worth reviewing the failure of stair structures in buildings in Christchurch NZ. Based on these findings, we allow the stair at the lower landing to slide and not become a stiff and potentially premature failure in the building The mass needs to be considered The...
  3. brizstruct

    AS3600 - 2018 Amendment 2 Draft

    Regarding the tilt up wall concept, no tension is implied under the changes and I assume that will need to be checked under the above changes. Shear will be applied. Tilt Up walls are typically supported at the two bottom corners.
  4. brizstruct

    AS3600 - 2018 Amendment 2 Draft

    Rapt Thank you for the link to Amdt 2 Apologies as I know this is out of your area but, I have a question on the alteration to Clause 11.7.5 and want to check if my interpretation is correct Paragraph 1 is unchanged:- (Hence where tension exists under any eq loadcase, Ast dowel>Ast wall) New...
  5. brizstruct

    AS3700-2018 and its amendment by the NCC

    Hi Rapt I understand that NCC can, should they wish, make up their own rules. I can remember a few occasions where amended codes took a while to be included in the Building Code of Australia However, it would be valuable if NCC provide commentary on why they have moved away from adopting a...
  6. brizstruct

    AS3700-2018 and its amendment by the NCC

    If someone is able to explain why NCC is overriding the standard (and can do this without needing future legal advice I would love to know the logic. As a personal opinion, I think that the small diameter ties in blockwalls would interfere with the core filling density and reduce the strength of...
  7. brizstruct

    How is Bondek/Condek Fixed to a brick structure

    Dan Bondek Condeck are attached using shear studs if composite action is required in teh steel beam. The shear studs are usually attached after the decking is laid by flash welding Where supported on Brick, slip joints are usually installed (Refer to stramit and bluescope web sites for some...
  8. brizstruct

    Ties in concrete columns

    All, I can't see how ties can be avoided as per the standard. The code is explicit and I am yet to find research that would suggest otherwise. Ties provide a) Restraint against local buckling of the bars b) Confinement of the inner core of the concrete c) Vertical alignment control of the bars...
  9. brizstruct

    Ties in concrete columns

    Thank you guys. I believe that the ties are required. THere is a need to provide local buckling restraint and the ligs also keep the vertical alignment try. With lapped splices there is a need to provide restraint for the bars at that point so I didn't see it being a solution. I was wanting to...
  10. brizstruct

    Ties in concrete columns

    We are looking at a project where the EOR has designed columns without intermediate ties as required by the code. Bars are not bundled and details are Column size 32"x32". Single #8 bars at 6" ctrs with only an outer tie. In the commentary to 318-77 there is a suggestion that ommission of...
  11. brizstruct

    In Situ Concrete Testing

    Suspended slab All poured same day Top surface of 5mm has been water blasted off Am conerned about what is underneath Cores not taken yet Trying to resolve methodolgy Thanks for the thread link
  12. brizstruct

    In Situ Concrete Testing

    It was rain effected during placement. The Superintedent instructed them to cease work but they did not. There is now a dispute adn I would like a rational and justifiable basis for the next part of the "discussion".
  13. brizstruct

    In Situ Concrete Testing

    I have asked a contractor to core sample a concrete slab that was rain effected. I am concerned about porosity adn would like to test for density. If there is anyone with guidance or suggestions I would appreciate the input

Part and Inventory Search

Back
Top