Hi members,
I am working on one debottleneck existing SCOT unit revamp project.
For the low-pressure supply from upstream, we need one new tail gas blower to push the gas through the downstream system.
The problem is, there are 505 kg/hr (8500 wtppm) H2S and 480 kg/hr (8000 wt ppm) SO2, with...