The gas and electric lines are not a problem. We have had them checked out and know the about the clearance issue. That’s the reason for keeping the depth of the footing to a minimum. This is just a research phase. When and if the plan is implemented the design will be authorized by a...
Our library is limited to the AISC Manual of Steel Construction, as all 18 of us ae Mechanical Design Engineers (rail car construction). The AISC Manual refers to ACI 318 in the 1 paragraph section on anchor rods and bolts. I have no access to the ACI literature so any help locating the...
Is there a formula used in determining the strength of the pull out "cone"? Also once this is determined is there a specification on minimum bolt spacing. My current design has bolts as close as 5", this was done to lower the stress in one of the anchors from 38ksi to 21ksi. I can have a depth...
I have designed a 65 ton bearing press and now must attach it to a foundation. As a mechanical my knowledge of concrete is limited. I have searched some literature an have some formulas, but I do not know if these are the best for my situation. The load is in the horizontal direction this...
I have designed a 65 ton bearing press and now must attach it to a foundation. As a mechanical my knowledge of concrete is limited. I have searched some literature an have some formulas, but I do not know if these are the best for my situation. The load is in the horizontal direction this...