Basically I am trying to set up a schedule for a resource like a CNC, but I want to update the actual times so that the tasks roll up/down so that the operator is maximizing his time.
Right now when I have a task that takes 6 hours, Project will split the time if it cannot be completed in the...
I have several tasks that cannot be started unless it can be finished in the same day. I want to link the task, but when I do it wants to split the task over two days. How can I acomplish this?