Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. DaveGeneski

    Spacing between tasks on gant chart view

    I decided to lay out a timeline for my board members using the time scale section of the gant chart view. When I added the name to a few of the high level tasks it made all of my tasks that same heigth not just the ones that I added the name to. When I try to move the tasks back into a...
  2. DaveGeneski

    Actual start and actual finish dates are changing start & finish

    Thanks ProjConPro, MSPtrainer and mlmaclean I have a good understanding of how those fields work now. I will add baseline start and finish to my plan to show the difference between estimated and actuall. Thanks again
  3. DaveGeneski

    Actual start and actual finish dates are changing start & finish

    Yes I don't understand why it changes the start and finish. Since I originally predicted the start and finish they shouldn't change when I update the actual start and actual finish, but it does. I think MS Project is flawed in this way. Thanks
  4. DaveGeneski

    Actual start and actual finish dates are changing start & finish

    I added an actual start and actual finish columns to my project plan in the gant chart view. When I try to update the actual start and actual finish dates, it changes the start and finish dates. I must be doing something wrong. Any help would be appreciated. Thanks
  5. DaveGeneski

    Completing a task should set the actual finish date

    When completing a task project does is not changing the actual finish date to the date that I completed the task. According the reading I have done this should be defaulted?
  6. DaveGeneski

    Finish no earlier than, task will not change to another type

    As I input new tasks, Project seems to guess what type of task it needs to be. I many times need to change these to something that makes more sense. example: inputted a task that needs to be done by a certain date and project made the task a "finish no earlier than" with a date that should be...
  7. DaveGeneski

    Correct way to create a late task report of view

    I have been trying to use the print a report menu, current activities, slipping tasks template. I then edit that template and choose late/over budget tasks, but it still doesn't report correctly.
  8. DaveGeneski

    How do you manage work effort as compared to duration

    Thanks thats where I am trying to get. I am not sure where to input the work hours. Could you detail the correct way to input the work hours. Sorry for being novice at this.
  9. DaveGeneski

    Difference between work effort and duration

    Let me try this question again. Lets say I have one person scheduled from 02/01 to 04/01 to complete a task that will only take them 4 hours. How do I tell project that I am giving them two months to complete a 4 hour task. This same person may have 19 other task for that same period.
  10. DaveGeneski

    How do you manage work effort as compared to duration

    I like to put start and end dates on each task, thinking about how many days I am giving a resource to complete a task. I although do not know how to input the work effort it will take to complete the task during the duration. Please help as I need to do a resource risk analysis and dont know...

Part and Inventory Search