I use P3
but EV will not give u a % as to where u should be.
i just heard that there is a way to take the target and update it....not changing the target dates
i know theres a way to do it...i just have to figure it out
well...how would u know where your supposed to be % wise compared to where you are on the job?
im getting asked According to the plan where SHOULD we be...and where are we ACTUALLY...(percent wise)
I have my main schedule and my target schedule....how do I update the target schedule?
what im trying to do is have my main target percent complete and compare it to where the job should actually be via the target schedule
for example..I update my main schedule for march 15th...and we are...