Thanks Ahereng.
The Production Manager would say: "I am right anyway - even with your calculation - because 1450 divided by 1020 = 141,6%."
Yes the math is correct in both cases, but who is right in the end?
A company has set standards: 0,15789 ton/minute equivalent to 6,359 minutes/ton.
One day the results were:
Tons produced: 228
Minutes worked: 1020
The production manager says: “Great day!” “Our tons/minute was 228 tons / 1020 mins, resulting in 0,22359 ton/minute. That is a dazzling 41,6%...