  1. Londoner

    recurring task not workin as i would like

    when i set a task to recur for a meeting the duration is not right. to test i set a simple 8 hr 2 day task and recurring it over 2 days with resource on 4 hrs shows duration 1.5 not 1
  2. Londoner

    MS Project 2003 - Consolidated Files

    Im having a mojor prob with recurring task a 2 dat task 8 hrs a day - when set as recurring task with resource on 4 hrs a day - shows duration of 1.5 days instead of 1 - help pls this is just a sample - im trying to get someone in for meetings only - so recurring task and the duration is way...