Thanks to all of you who responded. As it turned, out the owner and his representative came to their senses. There will be no L.D.'s after all. They even extended the final completion date to account for days lost to rain, unforeseen conditions, extra work etc...
I have used Quest,Paydirt and Agtek. In my mind there is no equal to Agtek. The software is more intuitive and much more user friendly than the others you mentioned.
I have exceeded the interim completion date on a project. The owners representative wants to assess a penalty of $1,000 per working day for each day we exceed the interim completion date. We encountered unforeseen conditions and excessively wet weather. What are my options when negotiating...