  1. dario1973

    Gas turbine in FSNL during steam piping cleaning

    Unfortunally I haven'this system but I have had from the contractor the confirmation about the possibility to blow the HP and LP system. They have some doubt about the IP system. Bye
  2. dario1973

    Gas turbine in FSNL during steam piping cleaning

    I'll follow Your advise. Thanks a lot and see You soon. Bye, Dario
  3. dario1973

    Gas turbine in FSNL during steam piping cleaning

    No, I'm not going to get base load because I haven't the availability of the substation. My doubt was realted to the fact that probably if in condition of base load the flue gas discharge of the GT is lower than the others GT and in FSNL I could have the same gap or higher. But, thinking to Your...
  4. dario1973

    Gas turbine in FSNL during steam piping cleaning

    I've another source of power from another existing substation. Thanks a lot. I have another question regarding the exhaust gas at the outlet of the gas turbine (V94.3A2): with GT26 and MS9001 FA there are no problem because the outlet temperature is high then the V94.3A2' one (in base load...
  5. dario1973

    Gas turbine in FSNL during steam piping cleaning

    Dear all, please help me to find a solution to this question. If We are in the steam blowing phase of BOP and HRSG and there's no availability of the electrical substation, it's possible to run the GT in FSNL during several blowing? Tha gas turbine is a V94.3A2. There's some problem...