Thanks for the feedback Rustbuster. As expected, client QC rejected latest films, although RT techs claim all necessary holes visible. I myself can see 8 of 10 necesary 2T holes. NDE contractor will be sending to their Level III for review, but I have asked them to also shoot the welds in...
Can anyone clarify or define "display" as it relates to viewing the Essential Hole for an IQI as it relates to ASME Section V Article II Radiography?
We are currently having a dispute with our clients QC rep and our 3rd Party NDE company over which wire or hole can be seen on 2" Schedule 10S...