Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. cwhit03

    kwh to kw demand chart

    I was wondering if anyone out there has a chart for residential demand based on either house square footage or kilowatt hours. I have a kwh to kw demand chart from Progress Energy, however this chart is from 1988 and the kwh only goes to 4000. I was looking for a more updated table possibly.
  2. cwhit03

    Problem on Wye-Wye Bank

    And A to N , B to N , C to N would still remain 120V based on the internal connections of the transformers. THe swapped connection on the third transformer is still 120V across the x1 and x2 postion, just the polarity is opposite. So to reiterate, with the secondary bushings as follows...
  3. cwhit03

    Problem on Wye-Wye Bank

    Ok now I see the phasor diagram and I understand the voltage vectors. Assuming the 0, -60, and -120 phase shifts, what would the phase to phase voltages be for A to B, B to C, and AtoC
  4. cwhit03

    Problem on Wye-Wye Bank

    Sorry I did not cleary state in my original post. The correct way to install was supposed to be: X1=a, X2=n X1=b, X2=n X1=c, X2=n The Journeyman put it on as x1=n, x2=c. I understand the 180 degrees and it being backwards. So the phase angles would be 0, -60, -120. Can explain in a little...
  5. cwhit03

    Problem on Wye-Wye Bank

    The tags were definitely correct. We were single phasing all customers. According to my foreman we were not getting the appropriate 3 phase voltage. I am in the process of getting the p-p voltage data. I will post when I get them.
  6. cwhit03

    Problem on Wye-Wye Bank

    Had a field connection done wrong the other day and wanted some input on the scenario. It was a wye-wye bank. Transformer # 1: H1=A, H2=N ===> X1=a, X2=n Transformer # 2: H1=B, H2=N ===> X1=b, X2=n Transformer # 3: H1=C, H2=N ===> X1=n, X2=c (Incorrect On Sec. Side) The field guy swapped...
  7. cwhit03

    Distribution Capacitor Bank

    I retrieved some recloser data yesterday for one of the feeders. The data was showing Phase A: PF=0.95, kW=258, kvar=85, KVA=269 Phase B: PF=0.56, kW=237, kvar=-346, KVA=421 Phase C: PF=0.51, kW=213, kvar=-356, KVA=416 The power factor on b and c phases were of some concern, and was...
  8. cwhit03

    Transformer Load

    I am interning a a power company and a lineman turned in a sheet the other day on a transformer he was called out on. They replaced it with a 50 KVA and the readings were as follows: X1=182 Amps (Phase to Ground), X3=189 Amps (Phase To Ground). This transformer is a 120/240 single phase...
Back
Top