Thanks a million, guys!
They've all been good stuff that you suggested. Now I start to get my head round what information is available and what is still needed in due course. Really appreciated your advices.
Thanks, Greg, for your attention.
We are close to mechanical completion at the moment. In terms of planning, there's a generic company commissioning procedure but this requires fine tune to be project specific. I will be starting with the planning and followed on to execution.
Hello all,
I am assigned to the commissioning team of a gas terminal with no previous commissioning experience. Is there any general tip for safe and successful commission / start up a gas plant? Is there any useful literature available on this topic.
Thanks very much for your help!