I2I,
Thank you for your comment.
I’m considering that this minimum line design by continuous bypass line with a fixed orifice.
Please refer to the attached file. (Attachment-1)
Reason:
Continuous bypass (not require air or electricity) may be lower cost method of protecting a pump when I...
Sorry, that my English language is not good but I will try.
In combine cycle power plant system, the condensate make-up system shall be provided to condenser to accommodate for HRSG(Boiler)blowdown and others cycle loss.
Please see the attached file for system diagram.
Conceptual design
Normal...