  1. jnobre

    Problem with MSP task durations against end dates

    when u specify 730d from for example 2008/Feb 22, MSP will put the end date in 2010/Dec 09, because it is assuming that u don't work at weekends, so you lose 2 days per week. If you specify 24mon, the end date (in my case) is 2009/Dec 24, because in the Tools->Options->Calendar my MSP defines 1...
  2. jnobre

    Leveling Resources in MSP 2003

    Hi! I'm managing a lot of small projects on a small team, sometimes having the need to have a global view of my team allocation. I thought MSP could help me on the task of controlling overallocation, but I met a couple of unexpected problems... For me, the most serious is the following: I have...