My company has purchased several IMO containers to be located on a site governed by NFPA 59A and such B31.3. The associated external tank piping on the IMO containers does not appear that it could have passed x-ray (root pass completely sugared, IF, etc). 49 CFR 178.274 nor 277 reference...
Thank you all for your responses.
I iwll need a new WPS PQR and WQR. Please help to clarify one last item for me. In what circumstances may the F grouping qualification be used to vary electrode? If a particular welder passes a WQR with F4 they are then qualified to weld the same process...
My question is regarding the essential variables of a WPS. B.31.1 is applicable code. The company has a WPS for 6010 downhill root and 7018 uphill out. The skilled welder has qualified to this procedure. The company would like to run a 6010 downhill out procedure for some upcoming work. It...