Thank you Guys for answering my questions. So if I eliminate the flat ridge board, it will look something like the attached picture. What about the connection at this point where the 4 hip beams meet and also at the walls?.
Regards...
Hello Guys;
I am currently working on a patio cover, please see the attached sketch. The architect wants me to remove two interior beams where the king posts are landing. I have seen several hip roofs without interior supports, but I just don't get how they are working. It seems that the...
I am using the Direct Design Method to determine the design moments for a Flat Slab with End Span Simply Supported on wall. My main concern is the detailing of the reinforcement. I am following ACI, Fig. 13.3.8 – and it appears that some areas of my slab will be unreinforced on the top, see...
Here is a Section that shows the Crain Rail Beam seating on top of the corbel ( now trying to replace it with a 1.5" thick plate). Like Teguci said, it will be welded to an embedded plate in the concrete.
Thanks...
Thanks "paddingtongreen"
Capacity of the Crane: 20 tons
Span : 55'
Lifting Height: 26'-0"
Weight of Trolley: 3,800 lbs
Weight of Bridge : 21,540 lbs
At the end, I ended up using a concentrated load of 74 kips to my supporting plate, 8" away from the back of my column.
Thanks
Hello
I designed a corbel for a bridge crane, but now the architect came back and said that he needed additional clearance (from the floor to the bottom of the corbel). They do not want to raise the roof, nor lower the slab. Being that the case, I need to find another way to support my bridge...
Hello Guys;
I am designing a two story Single Family Dwelling. The second floor has a 3'-0" projection out of the first floor. I have designed my shearwall, but I need to know how to strap it, I usually use an MST but in this case, I do not have where to strap it to.
Attached is a sketch, any...
I did a quick calc for a 6" cantilever concrete walkway, I would like to know if i am missing something. My minimum reinforcement looks iffy.
Thanks
Attached is the file,
Hello all;
I am designing an underground building which has a length of 200 feet and width of 60 feet. The height of the walls is 29 feet and it will have a dirt cover of 3 feet (The slab will see 3 feet of dirt). EFP pressure from the geo-report is 50 pcf/ft. Seismic is 15 H (inverted...
Thanks for the help guys. I spoke to the designer and told him to speak to welder and see the issues with good constructability.
Learned a lot, thanks
Tinguindin.
Hey Guys;
I have 61" circular plate that I will be adding stiffeners which are 5/8" thick x 12" and they vary in depth. See attached sketch.
I am the structural checking the calcs, which are fine, but is this constructable?
The spacing between the stiffeners are less than 4", and you would...
Thanks Ron;
6000 psi seems very high, but I will take into consideration the Windsor Probe.
Here is a Picture of what I am talking about.
Regards
http://files.engineering.com/getfile.aspx?folder=ae21be26-960a-40e6-88cc-9d70d94b3df7&file=Pipe_Support.JPG
Hey Guys;
I am working on a Pipe Support Design, I will be using Cable Pipe Hangers / Nylon Strap. The problem is that this is a 78" diameter concrete pipe that was built in 1913. I was able to find the plans, but no Concrete Strenght was specified. Any Ideas on the f'c?
Thanks
Regards
SlideRuleEra;
ACI 347-04.
3.7—Removal of forms and supports
"3.7.2.3—Because the minimum stripping time is a
function of concrete strength, the preferred method of determining stripping time is using tests of job-cured cylinders or concrete in place. When the contract documents do not specify...