Dear,
I used to set in the file/ options / schedule : default start time, default end time , hours per day, hours per week , days per month at the very beginning . Then I set up different calendars for different tasks. However, some calendars may have different start time, end time hours per...
Dear,
How to prepare construction programme under the same contract with different phases and completion dates. The programme should have multiple critical paths,one for each phase. Or else only one critical path to the latest completion date would not reflect the truth.
Previously, I use...